Fast-track Approvals Bill – the third fast-track consenting regime

Environment & Planning
Mar 08 2024
The fast-track consenting regime proposed by the National/ACT/NZ First coalition government was introduced to Parliament on 7 March 2024. The most awaited aspect of the Fast-track Approvals Bill – the list of projects to be fast-tracked – is blank at this stage.

A Fast-track Advisory Group of experts is to be established in the coming weeks to advise Ministers on what projects should be included in the legislation, following which the projects will be inserted into the schedules.

The key aspects of the Fast-track Approvals Bill are as follows.

Purpose

The Bill’s purpose is to provide a fast-track decision-making process that facilitates the delivery of infrastructure and development projects with significant regional or national benefits.

The Bill’s purpose has no reference to continuing to promote the sustainable management of natural and physical resources, unlike the COVID-19 Recovery (Fast-track Consenting) Act 2020 (FTA).

Processes covered

The Bill covers a much greater range of consents/approvals. In addition to resource consents and notices of requirement for designations under the RMA it includes consents/approvals under the Conservation Act 1987, Wildlife Act 1953, Freshwater Fisheries Regulations 1983, Reserves Act 1977, Heritage New Zealand Pouhere Taonga Act 2014, Exclusive Economic Zone and Continental Shelf (Environmental Effects) Act 2012, Crown Minerals Act 1991, and Fisheries Act 1996.

The Bill also makes a change to Environment Court processes under the Public Works Act 1981 for projects dealt with under the Bill.

The FTA only dealt with resource consents and notices of requirement for designations under the RMA.

Treaty of Waitangi

The Bill requires persons exercising functions under it to act in accordance with Treaty settlements and recognised customary rights.

The Bill does not contain a requirement to act in a manner that is consistent with the principles of the Treaty of Waitangi, unlike the FTA.

Projects

The Bill provides for two types of listed projects, and referred projects.

The two types of listed projects will be:

  • Part A – listed projects that can be referred straight to an Expert Panel.
  • Part B – listed projects that may be considered by the joint Ministers for referral to an Expert Panel.

The Bill contains criteria for being a referred project including whether the project will have significant regional or national benefits. An example of projects that may qualify include projects that will increase the supply of housing, address housing needs, or contribute to a well-functioning urban environment.

Projects are referred to Expert Panels for consideration.

Expert Panel

The Expert Panel will be set up in a similar way to Expert Consenting Panels under the FTA. However, Expert Panels will only be making recommendations to the ‘joint Ministers’ who will make the decisions.

The joint Ministers

For the most part, the responsible ‘joint Ministers’ under the Bill are the Ministers for Infrastructure, Regional Development and Transport. This is a move away from the Ministers for the Environment and Conservation under the FTA, although the latter will join the others for Wildlife Act matters.

Appeal rights

Appeal rights are available to the High Court on a point of law only. Rights of judicial review are not affected by the Bill.

Select committee process

The Bill has a strong focus on infrastructure and development and will be controversial. It has been referred to the Environment Committee for a select committee process and is open for submissions until 19 April 2024. Please get in touch if you would like to make a submission or discuss things further.