The new dawn of resource management law – consenting changes explained

Environment & Planning
Dec 10 2025
The Government has introduced the two Bills that are intended to replace the Resource Management Act 1991 (RMA), these being the Natural Environment Bill (NEA) and the Planning Bill (PA).

The intention appears for these bills to read for the first time in the coming week, and for them to be enacted in mid-2026.

This article focuses on the implications of the new Bills for the consenting process. You can also read our article on the structure and new policy and planning framework of the Bills here.

Consenting is managed under both Bills generally following the existing split between consents/permits managed by regional councils (managed under the NEA) and consents managed by district councils (managed under the PA).

Resource consents are out, resource and planning permits are in

The consenting framework under the Bills align with the Government’s goals of enabling development and reducing regulation. These changes impact what effects can be considered and who can be involved in resource consent processes. A change in language will occur as some resource consents will become resource permits. The key changes to the way of changes in which resource permits and considered and made are:

Activity statuses: Controlled and non-complying activity classifications cease to exist. At this time it is unclear if controlled activities would become permitted or restricted discretionary under the system.

Effects: The consideration of effects of an activity will be curtailed by the Bills. Positive effects, cumulative effects and natural hazards are now included. The following effects are excluded: visual amenity, financial viability, precedent effects, internal effects and less than minor adverse effects (unless they give rise to a cumulative effect that is more than less than minor).

Permitted activities: The objective is for more activities to be permitted activities, subject to conditions. This is reflective in the prescriptive wording of the Bills’ guidance on classification of activities which provides that an activity should be permitted if it is acceptable, anticipated, or achieves the desired level of use, development, or protection of the natural environment or the adverse effects of the activity are known and can be managed (i.e. by way of conditions in a permitted activity rule).

Affected persons: Only those who are materially affected can participate in a permit application process. Limited notification will only occur if effects are more than minor, which is a distinct lifting of the threshold required under the RMA which provides that a person is effected if the effects on them are “minor or more than minor”.

Public notification: The threshold for public notification has also been lifted and will only occur where the adverse effects of the proposed activity on natural resources or persons (NEA) or built environment (PA) are significant.

Consent terms: Carried over from reforms made to the RMA in mid-2025 permits associated with long lived infrastructure and renewable energy generation:

  • Have a starting point of a 35 year duration; and
  • In the case of structures in the coastal marine area or beds of lakes and rivers have a maximum duration of 50 years. For other activities associated with renewable energy generation or long lived infrastructure (i.e. permits relating to water) the NEA makes it clear that the maximum duration is 35 years.
What does this mean for existing resource consents?

Existing consents will carry over into the new system. This provides important continuity for consent holders. The question then arises – what happens to my resource consent application?

A transitional consenting process will apply from the period one month after the Bills receive royal assent and once the Order in Council repealing the RMA is made – this is referred to as the transitional period. This transitional process provides that the traditional RMA process for consent application is to be followed, albeit with some modification:

  • The Bills’ procedural principles are to be adhered to.
  • Certain effects are excluded from the scope of what can be considered.
  • The “special circumstances” criteria is removed from the public notification test.
  • Spatial plans and national standards are to be considered, once they are developed.

If an application is lodged and granted pre-transition period then it will be treated as a resource consent under the RMA. If an application is lodged pre-transition period, but a decision is made post-transition period then it will be treated as a permit under either the PA or NEA.

The return of the Planning Tribunal

The Planning Tribunal is getting a second-wind although only in name as the scope of its jurisdiction is different to the Planning Tribunal of years gone. This new tribunal will be established as a division of the Environment Court and will address administrative matters during the consent consideration process including, but not being limited to: requests for further information, interpretation of permit conditions, notification decisions, and striking out permit conditions that are deemed to be out of scope.

The Planning Tribunal will not hear appeals on plans, applications for notified permits (where there are third party participants, designations – nor will it deal with enforcement actions.

Automatic consent extension

Additionally, the Government introduced the Resource Management (Duration of Consents) Bill on 9 December 2025, which was passed under urgency on 10 December 2025 – the only stage left before it becomes law is for it to be given royal assent.

This Bill seeks to automatically extend resource consents that are due to expire before the new Bills are in force, and to deem that recently expired consents are reinstated and their expiry automatically extended. The Bill provides that:

  • Resource consents that would otherwise expire before 31 December 2027 are automatically extended until that date.
  • Recently expired resource consents (where an application for a replacement consent has been made under section 124 of the principal Act, but not yet determined) are deemed to be reinstated and extended until 31 December 2027.
  • Consents relating to freshwater are excluded from extension beyond a total duration of 35 years.

The resource management space is rapidly changing in New Zealand. We will continue to provide updates as the changes process. If you would like to know more about how these changes will affect you, or you would like assistance drafting a submission (once the submission period dates are announced), please contact one of our Resource Management team members below.

Scroll to Top